2008 Reporting Review
Recommendation 6 of 7

No:
From:
Year:
Status:
Owner:
6
2008 Reporting Review
2008
Closed
GOE

Recommendation

GOE to ensure completion of the Delivery Plans that implement the sustainability aspects of the Legacy Action Plan and PSA as soon as possible. The Delivery Plans need to be integrated with each other and demonstrate their linkages with related plans from other Key Stakeholders. They also need to form part of clear and effective reporting processes.

History

Status at 31 Mar 2013

Closed

Status at 01 Oct 2012

Closed

Status at 31 Mar 2012

Closed

Status at 31 Dec 2011

Closed

Status at 30 Sep 2011

Closed

Status at 30 Jun 2011

Closed

Status at 31 Dec 2010

Closed

HMG has revised its legacy delivery and governance arrangements again, setting up new boards to improve the management and reporting processes and assurance arrangements. Legacy promise 4.1 covered by PSA reporting process Legacy promise 4.2 dependant on DEFRA programmes which are developing and reports into the London 2012 Sustainability Group and onto OPLB Legacy promise 2 also covered by PSA reporting Closed (partly delivered through other means and partly that recommendations in the 2009 Annual Review take precedence)

Status at 30 Sep 2010

Closed

Status at 30 Jun 2010

Closed

Status at 31 Dec 2009

Progress Made

HMG has revised its legacy delivery and governance arrangements again, setting up new boards to improve the management and reporting processes and assurance arrangements. Legacy promise 4.1 covered by PSA reporting process Legacy promise 4.2 dependant on DEFRA programme which is developing Legacy promise 2 also covered by PSA reporting Progress Made