Recommendation
That the Olympic Delivery Authority, through the site-wide waste contractor, investigates the final use of all wood sent for recycling and reports accordingly.
History
Status at 31 Mar 2013
Complete
Status at 01 Oct 2012
Complete
Status at 31 Mar 2012
Complete
Status at 31 Dec 2011
Complete
Status at 30 Sep 2011
Complete
Status at 30 Jun 2011
Complete
Status at 31 Dec 2010
Complete
The ODA have reassessed the destination of the waste wood arising from their construction. Approximately two-thirds of the waste wood is going to recycling and one third is going to a location where 90-95% of it goes for recovery. The ODA have amended their figures to account for 92.5% of their waste that goes to this location being sent for recovery. This amounted to about 900 tonnes to September 2010. Complete
Status at 30 Sep 2010
Progress Made
Status at 30 Jun 2010
No Evidence Yet
Status at 31 Dec 2009
This review was published in March 2010. A statement on progress will be provided in the 2010 Annual Review.