Recommendation
That targets are set for the waste arising during the fitting out and removal of overlay and from temporary venues. The zero waste to landfill principle should be a key consideration when deriving these targets.
History
Status at 31 Mar 2013
Complete
Status at 01 Oct 2012
Complete
Status at 31 Mar 2012
Complete
Status at 31 Dec 2011
Complete
Status at 30 Sep 2011
Complete
Status at 30 Jun 2011
Complete
Status at 31 Dec 2010
Complete
Status at 30 Sep 2010
Complete
Status at 30 Jun 2010
Complete
Status at 31 Dec 2009
Complete
The London 2012 Sustainability Plan (December 2009) included the commitment to 'take reasonable endeavours to reuse or recycle at least 90 per cent, by weight, of the material arising from the installation and deconstruction of its temporary venues and overlay (stretch target)'. This is in addition to all hired goods being returned to the hire company. Complete