From:
Year:
Status:
Owner:
Recommendation
That long term management of the Olympic Park is resolved as soon as possible so that Park and Public Realm plans will be appropriate for legacy and will require a minimum amount of transformation.
History
Status at 31 Mar 2013
Closed
Status at 01 Oct 2012
Closed
Status at 31 Mar 2012
Closed
Status at 31 Dec 2011
Closed
Status at 30 Sep 2011
Closed
Status at 30 Jun 2011
Closed
Status at 31 Dec 2010
Closed
The ODA have produced a document 'Towards a 10 year management plan' which sets out how the site can be managed, including the ecological elements of the Park. The OPLC will be looking to procure an estates and facilities management contractor in late 2010. We are informed that this contract will include the management of the park, including the landscape and thus the biodiversity of the site. However, as this is still in development it is not currently possible to verify this. The level of resources available for the long term habitat management will be critical to ensuring that the BAP habitats are able to mature and achieve the appropriate SINC status. Work will be required in transformation to change habitats from Games-time habitats and concourse to legacy habitats that will meet the requirements of the BAP. Closed (recommendations from the Biodiversity review take precedence)
Status at 30 Sep 2010
Progress Made
Status at 30 Jun 2010
Progress Made
Status at 31 Dec 2009
Progress Made
A 10 year management plan for the Landscape and Public Realm in the Park has been developed, with the first phase of it submitted to PDT. The LMF and further detailed plans for the ongoing governance and management of the park are currently being reviewed by the OPLC. Progress Made