235 |
Annual |
2012 |
LOCOG
|
That LOCOG ensures that benchmarks are available for future Games to facilitate more responsible energy use.
Read more
|
Complete |
228 |
Legacy |
2012 |
LOCOG
|
That LOCOG, with appropriate support from Government, creates its own learning legacy that can be shared publicly beyond the IOC family to the events industry ...
Read more
|
Complete |
224 |
Sustainable Games Preparation |
2012 |
LOCOG
|
That the LOCOG City Operations team continue its work in ensuring appropriate plans for street cleansing, waste and recycling, accessibility, security and health and safety ...
Read more
|
Complete |
223 |
Sustainable Games Preparation |
2012 |
LOCOG
|
That LOCOG test the full Games-time waste and catering solutions during at least one event prior to the Games.
Read more
|
Not Achieved |
222 |
Sustainable Games Preparation |
2012 |
LOCOG
|
That LOCOG demonstrate that there are sufficient resources and expertise within all contractors and that their Sustainability Team has the capacity to manage all sustainability ...
Read more
|
Complete |
221 |
Sustainable Games Preparation |
2012 |
LOCOG
|
That LOCOG ensures that there is sufficient capacity to address accessibility issues during the construction and deconstruction of temporary venues and overlay and at Games-time.
Read more
|
Complete |
220 |
Sustainable Games Preparation |
2012 |
LOCOG
|
That LOCOG produce an energy management and conservation plan demonstrating how it will reduce carbon emissions by at least the amount that would have been ...
Read more
|
Complete |
218 |
Sustainable Games Preparation |
2012 |
LOCOG
|
That LOCOG clarify, monitor and report on where it will and will not be using alternatives to HFC, setting out the rationale for any cases ...
Read more
|
Complete |
216 |
Merchandise |
2011 |
LOCOG
|
That LOCOG work with their suppliers and licensees to communicate the complaints and dispute resolution process to workers throughout the supply chain, including at the ...
Read more
|
Complete |
215 |
Merchandise |
2011 |
LOCOG
|
That LOCOG work with their licensees to produce a series of case studies showing how the companies have responded to LOCOG's requirements and improved the ...
Read more
|
Not Achieved |
214 |
Merchandise |
2011 |
LOCOG
|
That LOCOG communicate the sustainability of their licensed products.
Read more
|
Not Achieved |
210 |
Annual |
2011 |
LOCOG
|
That LOCOG calculates the carbon that would have been saved through the renewable energy target and demonstrates how this carbon will be saved through reducing ...
Read more
|
Complete |
206 |
Annual |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group addresses delivery of the sustainability aspects of the Government legacy plan published in December 2010.
Read more
|
Closed |
204 |
Annual |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group should provide clear leadership over all aspects of sustainability (including health) and establish a mechanism to engage effectively with ...
Read more
|
Closed |
203 |
Inclusion and Healthy Living |
2011 |
LOCOG
BOA
BPA
|
That LOCOG, the British Olympic Association and the British Paralympic Association maximise the legacy of the Get Set programme and find partners to achieve this.
Read more
|
Complete |
201 |
Inclusion and Healthy Living |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group ensures that all healthy living commitments in the London 2012 Sustainability Plan are being actively monitored and progressed.
Read more
|
Complete |
200 |
Inclusion and Healthy Living |
2011 |
LOCOG
|
That LOCOG encourages existing venues that will host Olympic and Paralympic events during the London 2012 Games to implement lasting accessibility improvements.
Read more
|
Complete |
199 |
Inclusion and Healthy Living |
2011 |
LOCOG
GLA
GOE
|
That LOCOG allocates operational responsibility for the areas between transport nodes and the venues – the so-called Last Mile – and promptly identify and resolve ...
Read more
|
Closed |
198 |
Inclusion and Healthy Living |
2011 |
LOCOG
|
That LOCOG establishes mechanisms to ensure that late design changes to venues during overlay and fit-out take full account of accessibility and other sustainability requirements.
Read more
|
Closed |
197 |
Inclusion and Healthy Living |
2011 |
LOCOG
|
That LOCOG ensure that contract management processes are designed to achieve delivery of contractual commitments on accessibility and other sustainability objectives.
Read more
|
Complete |
196 |
Inclusion and Healthy Living |
2011 |
LOCOG
|
That LOCOG publish its Overlay Access File in a manner accessible for other event organisers to use and to enable it to be updated as ...
Read more
|
Complete |
195 |
Inclusion and Healthy Living |
2011 |
LOCOG
LLDC
|
That LOCOG and the OPLC [now LLDC] learn from the ODA's success in health and safety and adopt similar exemplary approaches to worker wellbeing. This ...
Read more
|
Complete |
193 |
Inclusion and Healthy Living |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Re-iteration of recommendation 12 from the 2009 Annual Review
http://www.cslondon.org/recommendations/detail/?id=184
That there is greater co-ordination of the healthy living agenda across Key Stakeholders, through existing groups, ...
Read more
|
Complete |
192 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG demonstrate how they will ensure that the flowers and medals can be used as symbols of sustainability at Games-time.
Read more
|
Complete |
191 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG contract management processes include effective assurance at point of delivery to ensure that all timber and timber products adhere to their sustainable sourcing ...
Read more
|
Complete |
190 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG makes better use of the Biodiversity Advisory Group, for example to promote biodiversity conservation associated with the Games.
Read more
|
Closed |
188 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG makes clear how the process for post-Games restoration of sites will be assured and resourced following its dissolution.
Read more
|
Complete |
184 |
Annual |
2010 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That there is greater co-ordination of the health agenda across Key Stakeholders, through existing groups, or possibly by establishing a Health Legacy board as part ...
Read more
|
Complete |
177 |
Annual |
2010 |
LOCOG
|
That LOCOG continue to explore opportunities with the legacy owners and the sport community to ensure the optimum long term benefit is achieved in lease/buy ...
Read more
|
Closed |
176 |
Annual |
2010 |
LOCOG
|
That LOCOG develop a suite of targets through each governance committee to reflect the emerging development of their priority sustainability strategies and operational programmes. The ...
Read more
|
Complete |
175 |
Annual |
2010 |
LOCOG
|
That LOCOG identify partner organisations with significant sustainability impacts and establish an engagement programme to ensure consistency.
Read more
|
Complete |
168 |
Waste |
2010 |
LOCOG
|
That LOCOG report on how materials under its direct control and influence are transported from venues during all phases of its Games operations and maximise ...
Read more
|
Complete |
162 |
Waste |
2010 |
London 2012 Sustainability Group
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group set out how the management of waste and resources in the post-Games bump-out/breakdown phase and subsequent transformation phase will ...
Read more
|
Complete |
160 |
LOCOG Procurement |
2010 |
LOCOG
|
That LOCOG urgently complete the Functional Sustainability Requirements for all Functional Areas and ensure they are embedded in Functional / Operational planning and tender documentation.
Read more
|
Closed |
159 |
LOCOG Procurement |
2010 |
LOCOG
|
That LOCOG strongly encourage their first tier suppliers to use CompeteFor with their addressable supply chain and that they actively encourage their commercial partners to ...
Read more
|
Complete |
158 |
LOCOG Procurement |
2010 |
LOCOG
|
That future iterations of the Sustainable Sourcing Code incorporate key sustainability issues, including water and air quality, and have a more explicit carbon section.
Read more
|
Complete |
157 |
LOCOG Procurement |
2010 |
LOCOG
|
That future iterations of the Sustainable Sourcing Code emphasise that sustainability has the same status as other business requirements and makes it clear which requirements ...
Read more
|
Complete |
156 |
LOCOG Procurement |
2010 |
LOCOG
|
That LOCOG review procurement activity to date and take any necessary retrospective action to ensure sustainability requirements are incorporated into contractual arrangements.
Read more
|
Closed |
154 |
Carbon |
2009 |
LOCOG
|
The residual footprint should be mitigated using a variety of techniques:
LOCOG should encourage the IOC to include carbon footprint measurement and management for future bids ...
Read more
|
Closed |
150 |
Carbon |
2009 |
LOCOG
|
The residual footprint should be mitigated using a variety of techniques:
Gold standard offsets, or other equally robust method, for flights for competitors and officials, in ...
Read more
|
Complete |
149 |
Carbon |
2009 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
The marginal carbon cost of decisions should be factored into operational decision making, taking into account life-cycle carbon impacts where possible and in a transparent ...
Read more
|
Closed |
148 |
Carbon |
2009 |
OB
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Responsibility for the whole residual footprint should rest with the Olympic Board, who should allocate responsibility for mitigation to the organisation best placed to achieve ...
Read more
|
Closed |
147 |
Carbon |
2009 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
CSL
|
Each individual Key Stakeholder should be responsible for reducing or avoiding emissions within their area of responsibility. The Commission for a Sustainable London 2012 has ...
Read more
|
Complete |
139 |
Annual |
2009 |
LOCOG
LDA
LLDC
|
LOCOG and the LDA [and now also the LLDC] should ensure that the resources and process to enable local employees and businesses to participate in ...
Read more
|
Complete |
133 |
Annual |
2009 |
ODA
LOCOG
|
The ODA and LOCOG should ensure a clear and consistent policy for mitigating the impacts of manufacture, use and disposal of temporary materials.
Read more
|
Complete |
129 |
Annual |
2009 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
All users of the London 2012 Brand should be required to demonstrate how they will contribute to the London 2012 Sustainability Plan and relevant objectives.
Read more
|
Not Fully Achieved |
125 |
Design |
2009 |
ODA
LOCOG
|
That LOCOG engage with the ODA on the accessibility of venues during Games time and how their operations will enable the venues to be fully ...
Read more
|
Closed |
123 |
Design |
2009 |
LOCOG
LLDC
|
That the LDA [now LLDC] and LOCOG produce a plan for the use of Games-time facilities and equipment which would be appropriate to be retained ...
Read more
|
Closed |
122 |
Design |
2009 |
ODA
LOCOG
LLDC
|
That there is a forum at which the ODA, LDA [now LLDC] and LOCOG consider the areas where there are opportunities for additional investment in ...
Read more
|
Closed |
121 |
Design |
2009 |
ODA
LOCOG
LLDC
|
That sustainability specialists are involved in the evaluation of design-related tenders to ensure that the relevant issues are considered at an early stage.
Read more
|
Complete |
120 |
Design |
2009 |
ODA
LOCOG
LLDC
|
That there is clear integration of sustainability objectives into the early design stages for the remaining developments and ongoing projects of all the Key Stakeholders. ...
Read more
|
Progress Made |
113 |
Design |
2009 |
LOCOG
|
That LOCOG should give consideration to the provision of additional accessible seating that will enable the accommodation of greater number than originally planned for where ...
Read more
|
Closed |
112 |
Design |
2009 |
LOCOG
|
That LOCOG engage a specialist resource to deal with inclusive design to ensure that accessibility and related issues are appropriately addressed.
Read more
|
Complete |
111 |
Design |
2009 |
LOCOG
|
That the findings of the Carbon Footprinting and Carbon Management Strategy are applied to LOCOG's design processes to minimise the carbon footprint prior to procurement.
Read more
|
Complete |
110 |
Design |
2009 |
LOCOG
|
That targets are set for the waste arising during the fitting out and removal of overlay and from temporary venues. The zero waste to landfill ...
Read more
|
Complete |
109 |
Design |
2009 |
LOCOG
|
That LOCOG explore the opportunities to influence the marketplace for the goods and services they require to seek to enable the requirements of the Sustainable ...
Read more
|
Complete |
103 |
Skills and employment |
2009 |
ODA
LOCOG
LDA
|
That the LDA, ODA, and LOCOG ensure that all tenders are placed on the CompeteFor on-line system and that clear regular reporting of winning contractors ...
Read more
|
Complete |
102 |
Skills and employment |
2009 |
ODA
LOCOG
|
That the ODA and LOCOG clarify their own commitment to apprenticeships given the LEST target of 4,000 apprenticeships and provide an outline programme of how ...
Read more
|
Complete |
91 |
Skills and employment |
2009 |
LOCOG
|
That LOCOG develop a broad pre-Games volunteering engagement programme to capture the enthusiasm of those already having registered expressions of interest as Games-time volunteers linking ...
Read more
|
Complete |
90 |
Skills and employment |
2009 |
LOCOG
|
That LOCOG develop a strategy to provide employment opportunities for residents in the five Host Boroughs building on the experience of the ODA, making use ...
Read more
|
Complete |
81 |
Annual |
2007 |
ODA
LOCOG
|
ODA/LOCOG to clarify how it will implement the commitment to access and mobility for Olympic Park and for temporary venues and temporary overlay.
Read more
|
Closed |
80 |
Annual |
2007 |
LDA
ODA
LOCOG
GOE
|
Develop clearly focused aspirations and targets for numbers of people to be trained, short and long term employment targets with particular reference to equalities.
Read more
|
Closed |
79 |
Annual |
2007 |
LDA
ODA
LOCOG
GOE
|
Ensure that the work of the various agencies operating in the skills and employment area (ODA, LDA, host boroughs, local voluntary sector, local education authorities, ...
Read more
|
Closed |
75 |
Annual |
2007 |
LOCOG
|
Make plans for implementation of a Games-time LEZ available after the Beijing Games.
Read more
|
Complete |
74 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Ensure that the health benefits of other workstreams are captured. For example, the impact on wellbeing from long term employment offered through the Employment and ...
Read more
|
Closed |
73 |
Annual |
2007 |
LOCOG
ODA
|
Work with food suppliers as early as possible to ensure there is an adequate supply chain to meet the ambitions for healthy, local and sustainable ...
Read more
|
Complete |
72 |
Annual |
2007 |
LOCOG
|
Develop the 2012 programme sustainable food strategy by 2008 with subsequent revisions after the Beijing Games.
Read more
|
Complete |
70 |
Annual |
2007 |
LOCOG
|
Produce plans for habitat and species management at other venues as part of the VEMP process.
Read more
|
Complete |
69 |
Annual |
2007 |
ODA
LOCOG
|
Set out how biodiversity is incorporated into the design process for venues and other development.
Read more
|
Complete |
68 |
Annual |
2007 |
ODA
LOCOG
|
Develop clear plans for how habitat is to be restored after construction on all sites.
Read more
|
Closed |
66 |
Annual |
2007 |
ODA
LOCOG
|
LOCOG should establish dialogue with the utility sponsor (appointed by LOCOG) and the utility partner (appointed by the ODA) in 2008 to understand how the ...
Read more
|
Closed |
65 |
Annual |
2007 |
LOCOG
ODA
|
Define energy targets for temporary venues and other venues requiring temporary overlay.
Read more
|
Closed |
62 |
Annual |
2007 |
LOCOG
|
Develop a clear communications strategy for the carbon strategy which is transparent about how carbon is to be managed, using terminology that is clear to ...
Read more
|
Complete |
61 |
Annual |
2007 |
LOCOG
|
Set out a timetable for refreshing the strategy to take account of emerging good practice
Read more
|
Complete |
60 |
Annual |
2007 |
LOCOG
|
Develop a proactive approach to linking the carbon strategy to the procurement process.
Read more
|
Complete |
58 |
Annual |
2007 |
LOCOG
|
Develop a clear definition of the footprint of the Games to include all relevant sources of greenhouse gas emissions that are created as a result ...
Read more
|
Complete |
57 |
Annual |
2007 |
LOCOG
|
Ensure that waste disposal is included in the carbon footprint to encourage prioritisation of re-use over recycling.
Read more
|
Complete |
55 |
Annual |
2007 |
LOCOG
|
Develop a strategy and standards for temporary overlay and temporary venues.
Read more
|
Closed |
54 |
Annual |
2007 |
ODA
LOCOG
|
Continue to develop a strategy for dealing with environmentally sensitive materials through the design and supply chain process.
Read more
|
Closed |
53 |
Annual |
2007 |
LOCOG
|
Develop a programme for minimisation and disposal of Games time waste in a manner that achieves the 'zero landfill' objective and stimulates investment in facilities ...
Read more
|
Closed |
39 |
Annual |
2007 |
LOCOG
|
Develop a Sustainability Management System that delivers adequate assurance in the absence of an ISO 14001 system and takes into account the requirements of BS ...
Read more
|
Complete |
38 |
Annual |
2007 |
LOCOG
|
Demonstrate commitment to SD principles by embedding SD into job descriptions, objectives, recruitment and personal development plans.
Read more
|
Complete |
37 |
Annual |
2007 |
LOCOG
|
Demonstrate how SD is being embedded into contractual commitments and into the process for measuring results in relation to sponsorship arrangements generally and in relation ...
Read more
|
Complete |
36 |
Annual |
2007 |
LOCOG
|
Ensure that Functional Area Business plans address clear SD targets, activities and outcomes in the next draft
Read more
|
Closed |
35 |
Annual |
2007 |
LOCOG
|
Demonstrate significant progress in developing the following strategic plans over the next 12 months:
• Food strategy to incorporate local, sustainable, healthy options which also minimise ...
Read more
|
Complete |
34 |
Annual |
2007 |
LOCOG
|
Publish specific SD objectives and targets.
Read more
|
Closed |
27 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Key Stakeholders to work with CSL to establish a pragmatic and meaningful reporting process.
Read more
|
Complete |
25 |
Annual |
2007 |
LOCOG
|
Build on the development of the London 2012 Sustainability Plan to describe how the wider strategic and legacy objectives related to the five key themes ...
Read more
|
Complete |
21 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Ensure that recruitment and succession plans are in place to provide continuity for key roles.
Read more
|
Closed |
18 |
Annual |
2007 |
LOCOG
|
The contribution made by sustainability partners should be clearly communicated through various media, including a section of the London 2012 website which also reports their ...
Read more
|
Closed |
17 |
Annual |
2007 |
ODA
LOCOG
|
ODA and LOCOG should develop a clear plan to collect information about labour standards in the supply chains of commercial partners and suppliers and, more ...
Read more
|
Closed |
11 |
Annual |
2007 |
ODA
LOCOG
|
LOCOG should establish dialogue with the utility sponsor (appointed by LOCOG) and the utility partner (appointed by the ODA) in 2008 to understand how the ...
Read more
|
Closed |
8 |
Annual |
2007 |
ODA
LOCOG
|
ODA and LOCOG should clearly set out their proposals for developing management systems (SMS) to cover all aspects of SD which will be subject to ...
Read more
|
Complete |
7 |
Annual |
2007 |
LOCOG
|
The full requirements of the London 2012 Sustainability Plan (SP) as they apply to LOCOG should be fully embedded in the next round of functional ...
Read more
|
Closed |
5 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Succession plans are put in place for all key positions essential to the delivery of SD outcomes. Also see recommendation 3.
Read more
|
Closed |
4 |
Annual |
2007 |
ODA
LOCOG
|
ODA and LOCOG should develop a clear statement of intent with respect to standards for temporary venues and temporary overlay.
Read more
|
Closed |