192 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG demonstrate how they will ensure that the flowers and medals can be used as symbols of sustainability at Games-time.
Read more
|
Complete |
191 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG contract management processes include effective assurance at point of delivery to ensure that all timber and timber products adhere to their sustainable sourcing ...
Read more
|
Complete |
190 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG makes better use of the Biodiversity Advisory Group, for example to promote biodiversity conservation associated with the Games.
Read more
|
Closed |
189 |
Biodiversity |
2010 |
GLA
|
That as part of developing plans to address the sustainability implications of all elements of City Operations, the GLA set out and implement clear plans ...
Read more
|
Closed |
188 |
Biodiversity |
2010 |
LOCOG
|
That LOCOG makes clear how the process for post-Games restoration of sites will be assured and resourced following its dissolution.
Read more
|
Complete |
187 |
Biodiversity |
2010 |
LLDC
|
That the habitats that are developed in legacy are in line with the habitat commitments set out in the Olympic Park Biodiversity Action Plan, providing ...
Read more
|
Complete |
186 |
Biodiversity |
2010 |
LLDC
|
That the body or bodies responsible for the Olympic Park in legacy set out and implement clear plans for how the habitat will be maintained, ...
Read more
|
Complete |
185 |
Biodiversity |
2010 |
ODA
|
That the ODA review existing procedures and controls to ensure they are suitable for managing the habitats during Park Operations and Transformation. This needs to ...
Read more
|
Complete |
184 |
Annual |
2010 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That there is greater co-ordination of the health agenda across Key Stakeholders, through existing groups, or possibly by establishing a Health Legacy board as part ...
Read more
|
Complete |
183 |
Annual |
2010 |
London 2012 Transport Partners
|
That the cost of public transport to the Games, combined with car park pricing be structured to ensure that travelling to the Games from outside ...
Read more
|
Complete |
182 |
Annual |
2010 |
LLDC
|
That the OPLC work with partners in the local community to ensure the Olympic Park is able to deliver zero carbon energy by 2016.
[This recommendation ...
Read more
|
Progress Made |
181 |
Annual |
2010 |
GOE
|
That GOE work with the rest of Government to ensure that the construction industry develops a consistent and effective approach to carbon management that includes ...
Read more
|
Not Fully Achieved |
180 |
Annual |
2010 |
GOE
|
That GOE work with the rest of DCMS to develop a consistent and effective approach to carbon management for major sporting events.
Read more
|
Not Achieved |
179 |
Annual |
2010 |
London 2012 Sustainability Group
|
That the London 2012 Sustainability Group, with input from relevant stakeholders, define the meaning of a 'blueprint for sustainable living' and develop a work plan ...
Read more
|
Closed |
178 |
Annual |
2010 |
London 2012 Sustainability Group
|
That the current London 2012 Sustainability Group be constituted as a formal legacy board or allocates clear responsibility for the promise to create a 'blueprint ...
Read more
|
Complete |
177 |
Annual |
2010 |
LOCOG
|
That LOCOG continue to explore opportunities with the legacy owners and the sport community to ensure the optimum long term benefit is achieved in lease/buy ...
Read more
|
Closed |
176 |
Annual |
2010 |
LOCOG
|
That LOCOG develop a suite of targets through each governance committee to reflect the emerging development of their priority sustainability strategies and operational programmes. The ...
Read more
|
Complete |
175 |
Annual |
2010 |
LOCOG
|
That LOCOG identify partner organisations with significant sustainability impacts and establish an engagement programme to ensure consistency.
Read more
|
Complete |
174 |
Annual |
2010 |
GOE
|
That GOE incorporate responses to the Commission's recommendations into the overall view of programme risk managed by OPPO.
Read more
|
Complete |
173 |
Annual |
2010 |
London 2012 Sustainability Group
|
That the London 2012 Sustainability Group establish a timely, clear, co-ordinated, funded, independent work programme to capture sustainability lessons learned and to set new standards ...
Read more
|
Closed |
172 |
Food |
2010 |
LLDC
|
Future development in the Olympic Park, led by the OPLC [now LLDC], should follow the example of the Athletes Village for which there is a ...
Read more
|
Progress Made |
171 |
Food |
2010 |
LLDC
GLA
|
The OPLC [now LLDC] should develop detailed design guidance for developers on how to incorporate food growing into their development plots, along the lines of ...
Read more
|
Progress Made |
170 |
Food |
2010 |
ODA
|
The ODA should contribute to the Learning Legacy from the Games and write up case studies for contractor catering so that the approach can be ...
Read more
|
Complete |
169 |
Waste |
2010 |
GLA
GOE
|
That City Operations teams, both in London and other locations around the country, set objectives for waste management that are consistent with those adopted by ...
Read more
|
Not Fully Achieved |
168 |
Waste |
2010 |
LOCOG
|
That LOCOG report on how materials under its direct control and influence are transported from venues during all phases of its Games operations and maximise ...
Read more
|
Complete |
167 |
Waste |
2010 |
ODA
|
That the ODA work with their waste contractor to measure, manage and report on the transport methods for materials leaving the Olympic Park site during ...
Read more
|
Complete |
166 |
Waste |
2010 |
ODA
|
That the Olympic Delivery Authority, through the site-wide waste contractor, investigates the final use of all wood sent for recycling and reports accordingly.
Read more
|
Complete |
165 |
Waste |
2010 |
ODA
|
That the Olympic Delivery Authority works with their waste contractor to reduce the quantity of waste being sent to conventional incineration.
Read more
|
Complete |
164 |
Waste |
2010 |
ODA
|
That the Olympic Delivery Authority reports separately on each of the three components of the construction waste target, being the proportions and tonnage of construction ...
Read more
|
Closed |
163 |
Waste |
2010 |
LLDC
|
That the Olympic Park Legacy Company develops an integrated waste and energy strategy for the legacy developments on the Olympic Park. This should use organic ...
Read more
|
Not Achieved |
162 |
Waste |
2010 |
London 2012 Sustainability Group
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group set out how the management of waste and resources in the post-Games bump-out/breakdown phase and subsequent transformation phase will ...
Read more
|
Complete |
161 |
Waste |
2010 |
LDA
|
That the London Development Agency, through the London Waste and Recycling Board, fund additional new commercially viable waste management facilities for the processing of organic ...
Read more
|
Not Achieved |
160 |
LOCOG Procurement |
2010 |
LOCOG
|
That LOCOG urgently complete the Functional Sustainability Requirements for all Functional Areas and ensure they are embedded in Functional / Operational planning and tender documentation.
Read more
|
Closed |
159 |
LOCOG Procurement |
2010 |
LOCOG
|
That LOCOG strongly encourage their first tier suppliers to use CompeteFor with their addressable supply chain and that they actively encourage their commercial partners to ...
Read more
|
Complete |
158 |
LOCOG Procurement |
2010 |
LOCOG
|
That future iterations of the Sustainable Sourcing Code incorporate key sustainability issues, including water and air quality, and have a more explicit carbon section.
Read more
|
Complete |
157 |
LOCOG Procurement |
2010 |
LOCOG
|
That future iterations of the Sustainable Sourcing Code emphasise that sustainability has the same status as other business requirements and makes it clear which requirements ...
Read more
|
Complete |
156 |
LOCOG Procurement |
2010 |
LOCOG
|
That LOCOG review procurement activity to date and take any necessary retrospective action to ensure sustainability requirements are incorporated into contractual arrangements.
Read more
|
Closed |