208 |
Annual |
2011 |
ODA
GOE
|
That the ODA, working with relevant government departments, gather evidence of the linkage between productivity, health, safety and sustainability and publish their findings as part ...
Read more
|
Complete |
207 |
Annual |
2011 |
ODA
|
That the ODA evaluate the 'as built' carbon footprints of at least two venues to include the Velodrome and the Aquatic Centre and publish the ...
Read more
|
Complete |
206 |
Annual |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group addresses delivery of the sustainability aspects of the Government legacy plan published in December 2010.
Read more
|
Closed |
204 |
Annual |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group should provide clear leadership over all aspects of sustainability (including health) and establish a mechanism to engage effectively with ...
Read more
|
Closed |
201 |
Inclusion and Healthy Living |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group ensures that all healthy living commitments in the London 2012 Sustainability Plan are being actively monitored and progressed.
Read more
|
Complete |
194 |
Inclusion and Healthy Living |
2011 |
ODA
GOE
|
That the ODA continue to work with the Health and Safety Executive to develop a programme to disseminate the learning on health and safety and ...
Read more
|
Not Fully Achieved |
193 |
Inclusion and Healthy Living |
2011 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Re-iteration of recommendation 12 from the 2009 Annual Review
http://www.cslondon.org/recommendations/detail/?id=184
That there is greater co-ordination of the healthy living agenda across Key Stakeholders, through existing groups, ...
Read more
|
Complete |
185 |
Biodiversity |
2010 |
ODA
|
That the ODA review existing procedures and controls to ensure they are suitable for managing the habitats during Park Operations and Transformation. This needs to ...
Read more
|
Complete |
184 |
Annual |
2010 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That there is greater co-ordination of the health agenda across Key Stakeholders, through existing groups, or possibly by establishing a Health Legacy board as part ...
Read more
|
Complete |
170 |
Food |
2010 |
ODA
|
The ODA should contribute to the Learning Legacy from the Games and write up case studies for contractor catering so that the approach can be ...
Read more
|
Complete |
167 |
Waste |
2010 |
ODA
|
That the ODA work with their waste contractor to measure, manage and report on the transport methods for materials leaving the Olympic Park site during ...
Read more
|
Complete |
166 |
Waste |
2010 |
ODA
|
That the Olympic Delivery Authority, through the site-wide waste contractor, investigates the final use of all wood sent for recycling and reports accordingly.
Read more
|
Complete |
165 |
Waste |
2010 |
ODA
|
That the Olympic Delivery Authority works with their waste contractor to reduce the quantity of waste being sent to conventional incineration.
Read more
|
Complete |
164 |
Waste |
2010 |
ODA
|
That the Olympic Delivery Authority reports separately on each of the three components of the construction waste target, being the proportions and tonnage of construction ...
Read more
|
Closed |
162 |
Waste |
2010 |
London 2012 Sustainability Group
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
That the London 2012 Sustainability Group set out how the management of waste and resources in the post-Games bump-out/breakdown phase and subsequent transformation phase will ...
Read more
|
Complete |
149 |
Carbon |
2009 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
The marginal carbon cost of decisions should be factored into operational decision making, taking into account life-cycle carbon impacts where possible and in a transparent ...
Read more
|
Closed |
148 |
Carbon |
2009 |
OB
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Responsibility for the whole residual footprint should rest with the Olympic Board, who should allocate responsibility for mitigation to the organisation best placed to achieve ...
Read more
|
Closed |
147 |
Carbon |
2009 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
CSL
|
Each individual Key Stakeholder should be responsible for reducing or avoiding emissions within their area of responsibility. The Commission for a Sustainable London 2012 has ...
Read more
|
Complete |
146 |
Carbon |
2009 |
ODA
|
The ODA should calculate embodied emissions based on 'as built' data for at least one, and preferably more, significant permanent venues to enable future projects ...
Read more
|
Closed |
138 |
Annual |
2009 |
ODA
|
The ODA should apply lessons from early projects such as Orient Way and communicate them internally to other project teams and externally to the industry.
Read more
|
Complete |
136 |
Annual |
2009 |
ODA
|
The ODA must ensure that the implications of the emerging legacy waste strategy are reflected in the design and build of the Olympic Village and ...
Read more
|
Closed |
133 |
Annual |
2009 |
ODA
LOCOG
|
The ODA and LOCOG should ensure a clear and consistent policy for mitigating the impacts of manufacture, use and disposal of temporary materials.
Read more
|
Complete |
129 |
Annual |
2009 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
All users of the London 2012 Brand should be required to demonstrate how they will contribute to the London 2012 Sustainability Plan and relevant objectives.
Read more
|
Not Fully Achieved |
125 |
Design |
2009 |
ODA
LOCOG
|
That LOCOG engage with the ODA on the accessibility of venues during Games time and how their operations will enable the venues to be fully ...
Read more
|
Closed |
122 |
Design |
2009 |
ODA
LOCOG
LLDC
|
That there is a forum at which the ODA, LDA [now LLDC] and LOCOG consider the areas where there are opportunities for additional investment in ...
Read more
|
Closed |
121 |
Design |
2009 |
ODA
LOCOG
LLDC
|
That sustainability specialists are involved in the evaluation of design-related tenders to ensure that the relevant issues are considered at an early stage.
Read more
|
Complete |
120 |
Design |
2009 |
ODA
LOCOG
LLDC
|
That there is clear integration of sustainability objectives into the early design stages for the remaining developments and ongoing projects of all the Key Stakeholders. ...
Read more
|
Progress Made |
108 |
Design |
2009 |
ODA
|
That a presentation be produced to set out the overall park design and how all elements link together. All venues and the park and public ...
Read more
|
Complete |
107 |
ODA Procurement |
2009 |
ODA
LDA
|
That, as part of the longer term evolution of CompeteFor, it is utilised to encourage and promote additional environmental criteria to drive improvements in businesses ...
Read more
|
Closed |
106 |
ODA Procurement |
2009 |
ODA
|
That the ODA has a system to manage procurement risk and delivery of the sustainability objectives and standards throughout their supply chain.
Read more
|
Complete |
105 |
ODA Procurement |
2009 |
ODA
|
That the ODA ensures that the risk of not achieving its sustainability standards is mitigated where the contractual arrangements do not mandate specific targets, such ...
Read more
|
Complete |
104 |
ODA Procurement |
2009 |
ODA
|
That the achievement of a BREEAM excellent rating be specified in all permanent venue contracts
Read more
|
Closed |
103 |
Skills and employment |
2009 |
ODA
LOCOG
LDA
|
That the LDA, ODA, and LOCOG ensure that all tenders are placed on the CompeteFor on-line system and that clear regular reporting of winning contractors ...
Read more
|
Complete |
102 |
Skills and employment |
2009 |
ODA
LOCOG
|
That the ODA and LOCOG clarify their own commitment to apprenticeships given the LEST target of 4,000 apprenticeships and provide an outline programme of how ...
Read more
|
Complete |
101 |
Skills and employment |
2009 |
ODA
|
That the ODA and partners establish an open single regular briefing session for stakeholders based on reporting of a standard suite of key indicators and ...
Read more
|
Complete |
81 |
Annual |
2007 |
ODA
LOCOG
|
ODA/LOCOG to clarify how it will implement the commitment to access and mobility for Olympic Park and for temporary venues and temporary overlay.
Read more
|
Closed |
80 |
Annual |
2007 |
LDA
ODA
LOCOG
GOE
|
Develop clearly focused aspirations and targets for numbers of people to be trained, short and long term employment targets with particular reference to equalities.
Read more
|
Closed |
79 |
Annual |
2007 |
LDA
ODA
LOCOG
GOE
|
Ensure that the work of the various agencies operating in the skills and employment area (ODA, LDA, host boroughs, local voluntary sector, local education authorities, ...
Read more
|
Closed |
74 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Ensure that the health benefits of other workstreams are captured. For example, the impact on wellbeing from long term employment offered through the Employment and ...
Read more
|
Closed |
73 |
Annual |
2007 |
LOCOG
ODA
|
Work with food suppliers as early as possible to ensure there is an adequate supply chain to meet the ambitions for healthy, local and sustainable ...
Read more
|
Complete |
71 |
Annual |
2007 |
ODA
|
Ensure biodiversity issues are effectively managed in the development of Prescott Lock.
Read more
|
Complete |
69 |
Annual |
2007 |
ODA
LOCOG
|
Set out how biodiversity is incorporated into the design process for venues and other development.
Read more
|
Complete |
68 |
Annual |
2007 |
ODA
LOCOG
|
Develop clear plans for how habitat is to be restored after construction on all sites.
Read more
|
Closed |
67 |
Annual |
2007 |
ODA
LLDC
|
As part of the Legacy Masterplan Framework, clarify what resources will be available and which agency will be responsible for managing the implementation of the ...
Read more
|
Closed |
66 |
Annual |
2007 |
ODA
LOCOG
|
LOCOG should establish dialogue with the utility sponsor (appointed by LOCOG) and the utility partner (appointed by the ODA) in 2008 to understand how the ...
Read more
|
Closed |
65 |
Annual |
2007 |
LOCOG
ODA
|
Define energy targets for temporary venues and other venues requiring temporary overlay.
Read more
|
Closed |
64 |
Annual |
2007 |
ODA
|
Ensure that the ODA energy scheme is developed to utilise alternative fuel sources over time and during legacy.
Read more
|
Closed |
63 |
Annual |
2007 |
ODA
|
Continue the good work to incentivise the Energy Services Company (to be appointed by the ODA) to deliver higher levels of carbon reduction.
Read more
|
Closed |
54 |
Annual |
2007 |
ODA
LOCOG
|
Continue to develop a strategy for dealing with environmentally sensitive materials through the design and supply chain process.
Read more
|
Closed |
33 |
Annual |
2007 |
ODA
|
Clarify objectives and responsibilities and targets for temporary venues and overlay.
Read more
|
Closed |
32 |
Annual |
2007 |
ODA
|
Ensure that shortage of information on legacy use of facilities does not preclude the business case for sustainable options by working with a range of ...
Read more
|
Closed |
31 |
Annual |
2007 |
ODA
|
Ensure that the recommendations highlighted in this report and in the emerging Legacy Masterplan Framework are taken into account in procurement specifications and design briefs ...
Read more
|
Closed |
30 |
Annual |
2007 |
ODA
|
Demonstrate commitment to SD principles by embedding SD into job descriptions, bonuses, objectives, recruitment and personal development plans, induction and training.
Read more
|
Complete |
29 |
Annual |
2007 |
ODA
|
Focus on recruitment of long term staff to support this agenda and procurement of resources required to support through service contracts and consultancy. Propose clear ...
Read more
|
Complete |
28 |
Annual |
2007 |
ODA
|
Ensure that sub-project specific plans contain detailed SD targets using guidance and co-ordination from the SD team. Summarise detailed targets and objectives to act as ...
Read more
|
Complete |
27 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Key Stakeholders to work with CSL to establish a pragmatic and meaningful reporting process.
Read more
|
Complete |
21 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Ensure that recruitment and succession plans are in place to provide continuity for key roles.
Read more
|
Closed |
17 |
Annual |
2007 |
ODA
LOCOG
|
ODA and LOCOG should develop a clear plan to collect information about labour standards in the supply chains of commercial partners and suppliers and, more ...
Read more
|
Closed |
11 |
Annual |
2007 |
ODA
LOCOG
|
LOCOG should establish dialogue with the utility sponsor (appointed by LOCOG) and the utility partner (appointed by the ODA) in 2008 to understand how the ...
Read more
|
Closed |
8 |
Annual |
2007 |
ODA
LOCOG
|
ODA and LOCOG should clearly set out their proposals for developing management systems (SMS) to cover all aspects of SD which will be subject to ...
Read more
|
Complete |
6 |
Annual |
2007 |
ODA
|
Clear and specific SD objectives and targets should be embedded in ODA sub-project plans, with associated personal objectives, recruitment and training to ensure appropriately skilled ...
Read more
|
Complete |
5 |
Annual |
2007 |
ODA
LOCOG
GLA
GOE
LDA
LLDC
|
Succession plans are put in place for all key positions essential to the delivery of SD outcomes. Also see recommendation 3.
Read more
|
Closed |
4 |
Annual |
2007 |
ODA
LOCOG
|
ODA and LOCOG should develop a clear statement of intent with respect to standards for temporary venues and temporary overlay.
Read more
|
Closed |