Recommendation
That the ODA work with their waste contractor to measure, manage and report on the transport methods for materials leaving the Olympic Park site during construction and aim to increase the quantity transported by sustainable means (rail or water).
History
Status at 31 Mar 2013
Complete
Status at 01 Oct 2012
Complete
Status at 31 Mar 2012
Complete
Status at 31 Dec 2011
Complete
Status at 30 Sep 2011
Complete
Status at 30 Jun 2011
Complete
Status at 31 Dec 2010
Complete
Figures for the method of removal of waste have been provided to the Commission. Whilst barge transport during 2010 was still significantly lower than road movements it did achieve approximately 25% during 2010. This is higher than the figures quoted to the Commission during the waste review and represents an improvement in performance. The number of road movements has also decreased since the early operations through onsite compaction of waste materials. The wharf has now closed and all movement will have to be by road, as movement by rail has not been possible. Complete
Status at 30 Sep 2010
Progress Made
Status at 30 Jun 2010
Progress Made
Status at 31 Dec 2009
This review was published in March 2010. A statement on progress will be provided in the 2010 Annual Review.